SOMA

Glossary

Estimate to Complete (ETC)

The expected cost to complete all remaining project work from the current data date to the end.

Maintained by Adam O’NeillDirector, QRA SpecialistLast reviewed

Estimate to Complete (ETC) is the expected cost of finishing all remaining work. It feeds directly into the Estimate at Completion: EAC = AC + ETC. ETC can be derived in two main ways. The formulaic approach uses EVM indices: ETC = (BAC − EV) ÷ CPI, which assumes the remaining work will be completed at the same efficiency as work to date. The bottom-up approach has the project team re-estimate the remaining work in detail — re-planning from the current position — and the sum of those estimates becomes ETC. The bottom-up approach is more work but more accurate when the project's circumstances have changed materially.

The choice between formulaic and bottom-up ETC depends on project stage and circumstances. In early and mid-project, when circumstances are broadly as planned and CPI is stable, the formulaic approach provides a reliable and unbiased forecast. After a significant scope change, disruption event, or change in execution strategy, a bottom-up re-estimate is necessary because historical CPI no longer reflects the conditions under which the remaining work will be done. Using a formulaic ETC through a material disruption event will produce a systematically incorrect EAC.

ETC should be reviewed and challenged at every reporting cycle. A common governance failure is allowing ETC to decrease by exactly the amount spent in each period — effectively reporting spend without updating the forecast. This produces an EAC that does not change over time, which gives false comfort that the project is on track. A realistic ETC will fluctuate as scope crystallises, risks mature, and performance data accumulates. If ETC is moving perfectly smoothly with no variation, either the project is unusually well-controlled or the estimates are not being genuinely revisited.

Used in practice

Need this on a live programme?

SOMA delivers this on live UK programmes — and trains teams in it. Where it fits:

Putting these techniques into practice?

SOMA provides independent project controls consultancy for UK programmes. We can help you apply QRA, EVM, schedule risk analysis, and more.