Glossary
NEC4 Compensation Event
Under NEC4, a defined event that entitles the Contractor to additional time, cost or both — assessed against the Accepted Programme in a structured, contemporaneous process.
NEC4 lists the specific events that qualify as compensation events — including changes to the Works Information, unforeseen physical conditions, weather that meets a defined severity threshold, and Project Manager or Client actions that affect the work. The contractual principle is that the Contractor should not bear risk for events outside their control, provided the event is properly notified and assessed through the compensation event process. Compensation events are the mechanism by which NEC4 allocates risk contemporaneously, rather than leaving disputes to be resolved retrospectively.
The process has specific time-bar clauses. A Contractor must notify a compensation event within eight weeks of becoming aware of it, or lose the right to additional time or cost in most circumstances. The Project Manager must respond within a defined period, either accepting the notification and requesting a quotation, or rejecting it with reasons. Assessing the compensation event uses the Schedule of Cost Components or Shorter Schedule of Cost Components depending on the option chosen, plus a properly quantified impact on the Accepted Programme.
For project controls, compensation events are where schedule and cost discipline either work together or fail together. A compensation event quotation needs a defensible impact analysis on the programme (showing the effect on planned completion, Key Dates, and critical path), a cost quotation built up from the Schedule of Cost Components, and a clear audit trail linking the event to the change in the Accepted Programme. Weak compensation event management is visible in poorly-structured schedule impact analyses, missing what-if scenarios, and programmes that are not updated to reflect implemented events — each of which becomes a dispute surface later in the contract.
Used in practice
Need this on a live programme?
SOMA delivers this on live UK programmes — and trains teams in it. Where it fits:
Related terms
Putting these techniques into practice?
SOMA provides independent project controls consultancy for UK programmes. We can help you apply QRA, EVM, schedule risk analysis, and more.