SOMA

Glossary

QCRA (Quantitative Cost Risk Analysis)

A Monte Carlo simulation of a project cost estimate that produces a probability distribution of outturn cost, rather than a single deterministic figure.

Maintained by Adam O’NeillDirector, QRA SpecialistLast reviewed

Quantitative Cost Risk Analysis (QCRA) applies Monte Carlo simulation to a project cost estimate to produce a range of possible outturn costs with associated probabilities. The output is typically an S-curve showing the probability of coming in on or under any given cost, with reference points at P50 (median), P80 and P95. The technique tells sponsors what level of contingency is required to achieve a specified confidence of not exceeding a budget, rather than relying on a deterministic point estimate plus an arbitrary percentage uplift.

A QCRA requires three-point estimates on cost line items (modelling estimating uncertainty), discrete risk events with probability and cost impact distributions (modelling risks that might materialise), and escalation assumptions modelled with their own uncertainty for long-duration projects. The analysis separates base estimate uncertainty from discrete risk events so that the client can see how much of the P80 position is driven by "the estimate is rough" versus "these specific risks might hit." Both contribute to contingency sizing but require different management approaches.

QCRA exists because deterministic cost estimates systematically understate the real cost distribution. A point estimate is the most-likely figure; the actual outturn distribution is right-skewed (more upside exposure than downside), which means the mean outturn cost is typically higher than the most-likely figure and the P80 is significantly higher than both. A traditional approach of taking the base estimate and adding a fixed percentage contingency (often 10% or 15%) loses sight of where the risk actually sits in the estimate, and produces a contingency figure that is either too low when the risk is genuinely material or unnecessarily high when the estimate is well-bounded. QCRA replaces the fixed-percentage convention with a distribution-aware contingency position.

The shape of the three-point distribution matters. Triangular and beta-pert are the most common choices on UK capital projects, with the choice reflecting how informative the most-likely figure is relative to the bounds. Correlation between cost elements that move together must be specified explicitly: materials inflation affects every materials-based line item, regulatory cost adders affect every related work package, and the default of zero correlation almost always understates the spread. The output is an S-curve plus a tornado chart of variance drivers. The S-curve gives the sponsor the confidence position at P50, P80 and P95. The tornado tells the project team which line items and discrete risks drive the variance. A QCRA without a tornado is delivering only half its value because sponsors want a contingency number but the project team needs to know what is driving it.

AACE Recommended Practice 57R-09 (Integrated Cost and Schedule Risk Analysis Using Risk Drivers and Monte Carlo Simulation of a CPM Model), 113R-20 (Integrated Cost and Schedule Risk Analysis and Contingency Determination Using Combined Parametric and Expected Value), and 123R-22 (Determining Project Cost and Schedule Contingencies Using Expected Value and Statistical Methods) are the methodology references that UK programmes typically align to. The leading tools are @Risk by Palisade (Excel-based, dominant in UK cost-focused QCRA work, handles probabilistic dependencies cleanly), Oracle Crystal Ball (also Excel-based, less common in UK practice), Acumen Risk by Deltek (handles cost and schedule in one workbench when integrated QCSRA is needed), and Safran Risk (typically schedule-led but capable of cost work). Tool choice is far less important than the calibration of the inputs and the discipline of the methodology.

A worked example clarifies the mechanics. Take a £250m water-treatment-works upgrade. The deterministic base estimate is built up from material quantities (£90m), labour (£60m), preliminaries (£25m), design and supervision (£15m), commissioning (£10m), and contractor profit (£50m). The QCRA inputs: three-point estimates per WBS line (e.g. materials 80/90/110, capturing commodity-price uncertainty over the build period); discrete risks including a 40% probability of contaminated-ground discovery costing £8-20m, a 25% probability of a tender-market shift adding £15-30m to materials and labour combined, a 20% probability of a regulatory consenting delay adding £3-8m in preliminaries; correlation between materials and contractor profit (shared exposure to commodity prices and overhead margins). Running 50,000 Monte Carlo iterations produces an S-curve with P50 = £262m, P80 = £288m, P95 = £315m. The deterministic £250m has a 38% probability of being met. Contingency at P80 is £38m (15.2% of base estimate), of which £14m is from estimating uncertainty in the base lines and £24m is from the three discrete risks, a level of decomposition that lets the project team manage contingency drawdown by category rather than as a single bucket.

Common QCRA failures cluster around three problems. First, no separation of base estimate uncertainty from discrete risk events, so the analysis double-counts where line items already have contingency baked into rates that is then duplicated in the three-point distribution. Second, zero correlation across the board for convenience, which understates the spread because real projects bunch risks around common causes. Third, a risk register copy-pasted from a template with generic risks that produce generic results, which the discriminating reader recognises in seconds. A defensible QCRA separates base estimate uncertainty from discrete risks cleanly, specifies correlation explicitly with reasoning, and uses a risk register built from this specific programme's delivery experience.

QCRA is most useful when the sponsor needs to make a funding decision that must stand up to scrutiny — HM Treasury Green Book business cases, IPA gate submissions, investment committee papers, and board-level capital approval. A QCRA that produces a P80 cost position the client can defend is worth considerably more than a QCRA that produces a number the investment team finds uncomfortable and therefore ignores. The discipline of the method — AACE-standard three-point estimates, transparent assumptions, explicit correlation — is what makes the output defensible.

Practitioner guide

QSRA vs QCRA: Meaning, Methodology, and When Each Is the Right Answer

Read the practitioner guide →

Used in practice

Need this on a live programme?

SOMA delivers this on live UK programmes — and trains teams in it. Where it fits:

Frequently asked

What does QCRA stand for?
QCRA stands for Quantitative Cost Risk Analysis. It is a Monte Carlo simulation applied to a project cost estimate that produces a probability distribution of outturn costs, typically reported as P50 (median, 50% probability of not exceeding), P80 (80% probability), and P95 (95% probability). The output is an S-curve showing contingency requirement at any given confidence level, rather than a deterministic point estimate with a fixed-percentage uplift.
What is the difference between QCRA and QSRA?
QCRA is Quantitative Cost Risk Analysis, a Monte Carlo simulation of the project cost estimate to produce a probability distribution of outturn cost. QSRA is Quantitative Schedule Risk Analysis, a Monte Carlo simulation of the project schedule to produce a probability distribution of completion dates. Many programmes need both, run jointly as Integrated Cost-Schedule Risk Analysis (QCSRA) so that schedule risks correctly drive their cost consequences (delay-related preliminaries, escalation, finance costs).
What inputs does a QCRA need?
Three inputs. First, three-point estimates on cost line items (minimum / most-likely / maximum), capturing estimating uncertainty in the base estimate. Second, discrete risk events from the project risk register, with probability and cost impact distributions, mapped to the cost lines they would impact. Third, correlation structure between cost elements that move together. Materials inflation affects every materials line, regulatory cost adders affect every related package, and zero correlation across the board almost always understates the real spread.
How is QCRA contingency different from a fixed-percentage contingency?
A fixed-percentage contingency (e.g. 10% or 15% of base) is a convention that loses sight of where the risk actually sits in the estimate. QCRA contingency is the difference between the base estimate and the P80 (or other target) confidence position from the Monte Carlo run, a figure derived from the specific risks and uncertainties on this project. QCRA contingency can also be decomposed: at P80, how much is driven by estimating uncertainty in base lines versus how much is driven by discrete risk events. This decomposition lets the project team manage contingency drawdown by category rather than as a single bucket.
What software is used for QCRA in the UK?
The leading tools are @Risk by Palisade (Excel-based, dominant in UK cost-focused QCRA work), Oracle Crystal Ball (also Excel-based, less common in UK practice), Acumen Risk by Deltek (handles cost and schedule in one workbench, useful for integrated QCSRA), and Safran Risk (typically schedule-led but capable of cost work). Tool choice is less important than calibration discipline. The methodology reference standards are AACE International Recommended Practices 57R-09, 113R-20 and 123R-22.
When does a project need a QCRA?
QCRA is required when the sponsor needs to make a funding decision that must stand up to scrutiny. The common triggers are: setting contingency for a funding submission, satisfying HM Treasury Green Book expectations for risk and optimism-bias adjustment on high-cost / high-risk proposals, satisfying the IPA Cost Estimating Requirements for confidence ranges at SOC / OBC / FBC stage gates, board-level capital approval where the investment committee needs a defensible contingency figure, MoD CADMID Concept and Assessment-phase business cases, and SSRO non-competitive contract baseline-profit submissions.
What does a P80 QCRA position mean?
A P80 QCRA position is the cost figure at which the project has an 80% probability of completing on or below, and a corresponding 20% probability of exceeding. It is the most common UK convention for funding upper-bound sensitivity (although the IPA does not formally mandate P80, its written requirement is for the central estimate to be P50, with the confidence range expressed as percentage bands around the Anticipated Final Cost). Funding at P80 means accepting that one in five projects funded at that level will overrun. On a portfolio of comparable projects, P80 funding produces under-spends on most and over-spends on a few, which is a defensible portfolio position if the over-spends can be absorbed.

Putting these techniques into practice?

SOMA provides independent project controls consultancy for UK programmes. We can help you apply QRA, EVM, schedule risk analysis, and more.